Group Captive Solar in Tamil Nadu (2026)

How large industries in Chennai and Tamil Nadu buy solar power from an off-site plant they part-own: the 26% / 51% rules, what you invest, what you save, the charges involved, and when rooftop solar is the better choice.

By the Arka Solar Energy team · Updated 3 November 2026 · 11 min read

Many large factories in Tamil Nadu use far more electricity than their roofs can produce. A 1 MW rooftop plant may cover only 15–30% of a big HT consumer's annual use. Group captive solar solves this. Several consumers jointly own a share of a large solar (or wind-solar hybrid) plant elsewhere in the state, and the power is delivered to their factories through the grid under open access. Because the consumers are legally "captive" owners, they avoid some of the heaviest open access charges and can cut their power cost substantially.

Quick answer: under group captive, consumers must together hold at least 26% of the equity in the plant's special purpose vehicle (SPV) and consume at least 51% of its annual generation, roughly in proportion to their shareholding. In return, they are exempt from cross-subsidy surcharge and additional surcharge, which can make group captive solar meaningfully cheaper than HT grid power. It suits HT consumers with large, steady loads and limited roof space. Rooftop solar on your own premises is usually simpler and saves more per unit, so most businesses should use their roof first.

What is group captive solar?

In a captive arrangement, a business generates electricity for its own use. In group captive, a developer sets up a large solar or hybrid plant, usually ground-mounted in a high-irradiation part of Tamil Nadu, through an SPV. Several industrial and commercial consumers buy a minority stake in that SPV and sign long-term power purchase agreements, typically for 15–25 years. The power is wheeled through the TNPDCL and TANTRANSCO network and adjusted against each consumer's HT bill.

Tamil Nadu is one of India's most active group captive markets because of its large renewable base, especially wind, and its high HT industrial tariffs. Wind-solar hybrid group captive projects are common here because wind generates in the evenings and during the monsoon months, when solar output is lower.

The 26% equity and 51% consumption rules

To qualify as captive under the Electricity Rules, 2005:

Compliance is verified every year. If the conditions are not met, the power can lose its captive status and attract the surcharges it was exempt from, which can wipe out much of the saving. Good developers manage allocations and track compliance month by month.

Charges and savings in Tamil Nadu

The cost of group captive power is not just the PPA tariff. Your landed cost includes:

ComponentWhat it isApplies to group captive?
PPA tariffPrice per unit paid to the SPVYes
Transmission and wheeling chargesFor using the grid to carry power to your factoryYes
Transmission and distribution lossesPart of the power lost in transitYes
Banking chargesFor storing surplus units to use later in the billing cycle (8% in kind under TNERC's 2025 GEOA regulations)Yes, if you bank
Scheduling, metering and SLDC chargesOperational charges for open accessYes
Cross-subsidy surchargeCompensation to the DISCOM for consumers leaving the grid supplyNo (exempt for captive)
Additional surchargeFor the DISCOM's stranded supply commitmentsNo (exempt for captive)

Industry analyses have estimated that Tamil Nadu industries can save up to about ₹2 per unit with open access solar, and commercial consumers more, against grid tariffs. Actual savings depend on the PPA tariff, current TNERC charges, banking, your HT tariff (about ₹7.50 a unit for HT I industrial) and how well generation matches your consumption. Always compare offers on landed cost per unit, not the headline tariff.

Charges change: TNERC notified new Green Energy Open Access Regulations in 2025, covering eligibility, banking and charges, and open access charges are revised periodically. Ask any developer for a landed-cost calculation using the current TNERC orders, with a sensitivity for future changes.

What a business invests in group captive

Because the 26% rule applies to the SPV's equity, not the total project cost, the investment is much smaller than buying a plant outright. A typical SPV is funded about 70% by debt and 30% by equity. Captive users buying 26% of that equity therefore invest roughly 8% of the project cost.

Illustration: 1 MW share of a ground-mounted solar plantApproximate figure
Project cost attributable to 1 MW₹3.5–4.5 crore
Equity portion (about 30%)₹1–1.35 crore
Captive users' 26% of equityAbout ₹27–35 lakh
Annual generation from 1 MWAbout 15–17 lakh units

This is an illustration only. Actual equity requirements, plant costs and generation vary by developer, technology and location. The equity is typically returned at the end of the term, or as agreed in the shareholder agreement.

Group captive vs rooftop vs RESCO

Rooftop (CAPEX)Rooftop (RESCO)Group captive
Where the plant isYour roofYour roofOff-site, anywhere in Tamil Nadu
Upfront investmentFull plant costNone26% of SPV equity (about 8% of project cost)
Size limitYour roof area and connection limitsYour roof area and connection limitsCan cover most of your annual demand
Grid chargesNone for self-useNone for self-useTransmission, wheeling, losses, banking
Savings per unitHighestModerateModerate, depends on charges
ComplexityLowLowHigh: SPV, compliance, open access approvals
Best forAny business with a usable roofRoof available, no capitalLarge HT consumers whose demand exceeds roof capacity

For most businesses, the best approach is rooftop first, then group captive for the rest. Install as much rooftop solar as your roof and connection allow, then use group captive or hybrid open access to cover the remaining daytime and night-time demand. See zero-investment solar for factories (RESCO / OPEX) and rooftop solar plant costs.

Who group captive solar suits

Group captive is usually not suitable for LT consumers, small units or businesses that may relocate or shrink within the contract period.

How the group captive process works

1. Consumption study

Review 12–24 months of HT bills and time-of-day consumption to size your share and understand banking needs.

2. Compare rooftop and off-site options

Size the rooftop plant first, then work out how much demand is left for group captive.

3. Select a developer and project

Compare landed cost, technology (solar or wind-solar hybrid), track record, financial strength and compliance management.

4. Sign agreements

Share subscription and shareholders' agreement for the SPV equity, plus a long-term PPA with tariff, term, exit and compliance clauses.

5. Open access approvals

The developer applies for open access through the state's single-window process, with metering and scheduling arrangements in place.

6. Supply, adjustment and compliance

Generation is adjusted against your HT bill each billing cycle, and captive compliance is verified every financial year.

Risks and what to check before signing

  1. Landed cost, not tariff: insist on a per-unit landed-cost calculation under current TNERC charges.
  2. Regulatory change: how are changes in wheeling, banking or surcharges shared between you and the developer?
  3. Captive compliance: who tracks the 26% and 51% conditions, and who pays if they fail?
  4. Co-members: other consumers in the SPV affect compliance. Check exit and replacement provisions.
  5. Generation guarantee: minimum annual generation, with compensation for shortfalls.
  6. Demand changes: what happens if your consumption falls, or you sell or close a plant?
  7. Developer strength: execution record, balance sheet, and O&M capability over 25 years.
  8. Exit and equity return: how and when your equity is returned at the end of the term or on early exit.

Frequently asked questions

What is group captive solar in Tamil Nadu?

It is an arrangement where several consumers jointly own at least 26% of the equity in an off-site solar or hybrid plant and consume at least 51% of its output. The power reaches their factories through the grid under open access, and they are exempt from cross-subsidy and additional surcharges.

What are the 26% and 51% rules?

Under the Electricity Rules, 2005, captive users must together hold at least 26% of the equity share capital with voting rights in the generating company, and consume at least 51% of the electricity it generates over the financial year, roughly in proportion to their shareholding in group captive.

How much can a factory save with group captive solar?

It depends on the PPA tariff, current open access charges, banking and your grid tariff. Industry analyses have estimated savings of up to about ₹2 per unit for Tamil Nadu industries. Always compare offers on landed cost per unit.

How much do I need to invest in group captive?

Only your share of 26% of the SPV's equity, typically around 8% of the project cost attributable to your share. For a 1 MW share, that is roughly ₹27–35 lakh, depending on the project.

Is group captive better than rooftop solar?

Not usually on a per-unit basis. Rooftop solar used on site avoids grid charges and saves more per unit. Group captive is best for covering demand that your roof cannot, so most businesses should install rooftop solar first.

Who is eligible for green energy open access in Tamil Nadu?

Eligibility is set by TNERC's Green Energy Open Access Regulations, 2025, and applies mainly to HT and EHT consumers. Captive generating plants have a right to open access. Check the current regulations and your connection details with your developer.

Can group captive be combined with rooftop solar?

Yes. Many factories install rooftop solar to cover part of their daytime demand and use group captive or hybrid open access for the rest, including evening and night-time consumption through wind or banking.

Rooftop, RESCO or group captive: which suits your plant?

Arka Solar Energy is a solar EPC company in Chennai. Share 12 months of HT bills and we'll size the rooftop plant your premises can carry and show how much demand is left for off-site options, with the savings for each.

This guide is general information as of November 2026, not legal, regulatory, financial or tax advice. Captive rules, open access eligibility and charges are set by central rules, TNERC and TNPDCL/TANTRANSCO and change from time to time. Investment, cost and savings figures are illustrative. Verify current regulations and take professional advice before entering a group captive arrangement.